Proposal Submission Timeline
| 90-60 days | Notification to Research Office Staff |
| 60 days | Identify/contact possible external reviewers |
| 45 days | Draft budget (if subcontracts) |
| 30 days | Final subcontractor budgets |
| 30 days | Draft budget and justification |
| 25 days | Final title, start dates, UFirst info |
| 20 days | Subcontractor documents |
| 20 days | Final budget and justification |
| 15 days | Complete admin shell |
| 10 days | Letters of support |
| 7 days | All final documents |
| 6 days | (Research office proof/Format) |
| 5 days | Route in UFirst |
| 4 days | (Routing/Review/Corrections) |
| 3 days | DSP review and submission |
| 2 days | (Fix possible errors) |
| 0 days | Sponsor deadline |